Upgrade a Reduced-Capacity, Online Cluster

      +
      A cluster can be upgraded while still online, without additional nodes required — provided that it is permitted to serve data at reduced-capacity, for the duration of the cluster-upgrade.

      Understanding Reduced-Capacity Upgrade

      The context and overall requirements for upgrading a live cluster without the introduction of one or more additional nodes are described in Upgrade-Procedure Selection: this fully explains the node-by-node upgrade of the cluster, using swap rebalance to minimize overhead. It also explains how, if additional nodes are not available, the procedure can be completed with no more than the existing cluster-nodes, provided that the cluster can perform acceptably at reduced capacity, during the upgrade.

      The precise steps for this reduced-capacity procedure are provided on this page, below. A full understanding of the information in Upgrade-Procedure Selection should be acquired, before proceeding. The procedure assumes that:

      • The cluster to be upgraded must continue to serve data throughout the cluster-upgrade process.

      • No additional node is available, to act as a spare node. Therefore, a spare node must be created; by withdrawal of a node from the cluster — thereby reducing the capacity of the cluster.

      • During the cluster-upgrade process, swap nodes and upgraded nodes will be introduced to the cluster by the node-addition procedure; while failed over spare nodes and nodes to be upgraded will be withdrawn from the cluster by means of the node removal and swap rebalance procedures.

        For information on node-addition, see Clusters. For information on node-removal, see Removal. For information on swap rebalance, see Swap Rebalance.

      • Nodes will be upgraded one at a time.

      The overall procedure is described in six stages, below.

      Stage One: Prepare the Cluster

      Back up all cluster-data. This can be performed either with cbbackupmgr or with the Backup Service; and should be a full (rather than an incremental) backup.

      For example, to use cbbackupmgr to configure an archive and repository for the backup, a command of the following form should be entered:

      cbbackupmgr config --archive ${ABS_PATH_TO_ARCHIVE} --repo ${REPO_NAME}

      Here, ABS_PATH_TO_ARCHIVE is an absolute path to a filesystem location that will serve as the archive within which the backed up data will reside. The REPO_NAME is the name of the repository that will be associated with the location.

      Once the archive and repository have been created, a command such as the following performs a full backup:

      cbbackupmgr backup --archive ${ABS_PATH_TO_ARCHIVE} --repo ${REPO_NAME} \
      --cluster ${CLUSTER_ADDRESS} --username ${USERNAME} --password ${PASSWORD} \
      --full-backup

      Here, the CLUSTER_ADDRESS is the IP address or domain name of the cluster that is being backed up. The --full-backup flag ensures that the backup is indeed a full backup.

      For the equivalent procedure as performed by the Backup Service, see Run an Immediate Backup.

      Stage Two: Remove a Node

      Remove a node from the cluster. This node will function as a spare node; allowing swap rebalance to be performed on each successive node to be upgraded; and in consequence, the cluster will continue to serve data with reduced capacity. For information, see Using Spare Nodes.

      For examples of removing a node, see Remove a Node and Rebalance. To remove a node with the Couchbase CLI, a command such as the following can be used:

      couchbase-cli rebalance -c ${CLUSTER_NODE_HOSTNAME_OR_IP} \
      -u ${USERNAME} -p ${PASSWORD} \
      --server-remove ${TARGET_NODE_HOSTNAME_OR_IP}

      Here, the CLUSTER_NODE_HOSTNAME_OR_IP is the IP address or domain name of any node in the cluster. The NODE_HOSTNAME_OR_IP is the IP address or domain name of the node that is to be removed from the cluster.

      For a full description of steps whereby nodes can be removed from the cluster — using the UI, CLI, and REST API — see Remove a Node and Rebalance.

      From this point until the end of the cluster-upgrade process, the online cluster continues to serve data with its current number of nodes, which is one less than previously.

      Stage Three: Upgrade the Removed Node

      Upgrade the node that has just been removed, by proceeding as follows:

      1. Stop the couchbase-server.service service, on the node. Enter the following command:

        systemctl stop couchbase-server.service

        This stops the service; and so allows it to be restarted after reboot. Note that, optionally, at this point, the service can also be disabled; which prevents it from restarting after reboot. This may be useful if additional tasks, such as OS upgrade, need to be performed. If such disabling is desired, enter the following command:

        systemctl disable --now couchbase-server.service
      2. Back up the configuration files for the removed node. On a Linux system, these files are to be found in /opt/couchbase/var/lib/couchbase/config. Ideally, these should be backed up onto a different machine. The command takes the following form:

        cp -r /opt/couchbase/var/lib/couchbase/config ${PATH_TO_A_SAFE_LOCATION}/${NODE_IP}_config_files
      3. Uninstall couchbase-server and its dependencies from the removed node. Enter the command that is appropriate for the platform. Note that the following examples remove Enterprise Edition of Couchbase Server: to remove Community Edition, specify couchbase-server-community (instead of couchbase-server).

        • RedHat & Centos

        • Ubuntu & Debian

        yum autoremove couchbase-server
        apt autoremove --purge couchbase-server
      4. Manually remove files from /opt/couchbase. This folder contains configuration files for the previous server-version; which need to be overwritten by configuration files for the new version. If the administrator has manually included in this folder any files that were not provided by Couchbase Server, and need to be retained, these should be individually identified and backed up with with cbbackupmgr or with the Backup Service. Note also that care should taken regarding the potential removal of files used in network sharing.

        Enter the following command:

        rm -r /opt/couchbase
      5. Determine whether any other files, still resident on the node, need to be either removed, or backed up and removed. If such files exist, deal with them accordingly.

      6. Install Couchbase Server on the node. Follow steps 1, 2, and 3; provided in Install.

      7. Pin (or hold) automated Couchbase-Server updates for the node. This ensures that no further upgrade can occur to this node until the next time the administrator electively performs the process.

        RedHat & Centos

        For Couchbase Server Enterprise Edition, ensure that the package-name appears in the list that follows the exclude statement, in the file /etc/yum/yum.conf. For example:

        exclude=couchbase-server

        (For Couchbase Server Community edition, specify couchbase-server-community, instead of couchbase-server).

        Ubuntu & Debian

        For Couchbase Server Enterprise Edition, run the following command:

        apt-mark hold couchbase-server

        (For Couchbase Server Community edition, specify couchbase-server-community, instead of couchbase-server).

      8. Assuming that the couchbase-server.service service was stopped on the node to be upgraded prior to that node’s upgrade, restart the service.

        Note that if the service was also disabled, it must be re-enabled, prior to being started. To re-enable the service, if necessary, enter the following command:

        systemctl enable --now couchbase-server.service

        To restart the service, enter the following command:

        systemctl start couchbase-server.service

      Stage Four: Add Back the Upgraded Node, and Remove Another Node

      Add the upgraded, removed node back into the cluster, and remove a node that is currently part of the cluster. The node that is being added should be configured to run the same service (or services) on the node that is to be removed. For example, if the node to be removed is running the Data Service, configure the node to be added to run the Data Service. Couchbase Server will execute the rebalance as a swap rebalance, to maximize efficiency.

      For an overview of node-removal, see Removal; and for practical examples of performing removal, see Clusters; and for practical examples of node-addition, see Add a Node and Rebalance.

      Note that for the CLI and REST API, the staging of a swap rebalance requires two separate commands.

      • The first specifies that one or more nodes be added to the cluster: however, this command requires a subsequent rebalance to be performed, to complete the process.

        For an example of performing addition with the CLI, see Add a Node and Rebalance with the CLI. For an example of performing addition with the REST API, see Add a Node and Rebalance with the REST API.

      • The second command indeed specifies that subsequent rebalance, but also includes an instruction to remove one or more nodes from the cluster: therefore, as the rebalance occurs, it finalizes both node-addition and node-removal.

        For an example of using rebalance to remove a node with the CLI, see Remove a Node with the CLI. For an example of using rebalance to remove a node with the REST API, see Remove a Node with the REST API.

      Stage Five: Continually Repeat Stages Three and Four

      Repeat Stage Three: Upgrade the Removed Node and Stage Four: Add Back the Upgraded Node, and Remove Another Node until all nodes have been upgraded and added back into the cluster, except one.

      Stage Six: Add Back the Last Node

      When the last node to be upgraded has been upgraded, add this node back into the cluster without removing any other node; and perform a rebalance. This will be executed by Couchbase Server as a full rebalance.

      The cluster is now fully upgraded, and is at full capacity.